Polish power producer ZE PAK to switch unit at plant from coal to biomass

KONIN, Poland, Aug. 12, 2019 (Press Release) -On 2 July 2019, the Supervisory Board of ZE PAK S.A. accepted a detailed concept for the implementation of the investment in the Konin Power Plant, involving the modernization of the existing K7 coal boiler together with turbogenerators and, therefore, the creation of the second biomass-fired generating unit.

After the modernization, the boiler will cooperate with a 50 MWe turbogenerator producing electricity on an everyday basis. In emergency situations, and during planned repairs, the new unit will supply a turbogenerator producing heat and electricity for the city of Konin.

The process, which the Konin Power Plant is undergoing, is ...